Approval and Authorisation

The approval and authorisation procedures issued by the Department were for the design of steam boilers, unfired pressure vessels, and hoisting machinery, whereas the authorisation to install was issued for general machinery.

The guides and procedures for approval done by DOSH are as below:

  •  Introduction

    Approval of Personal Protective Equipment (KPD) is one of the needs and requirements of the Factories and Machinery Act 1967, Occupational Health and Safety Act 1994 and Regulations there under. Where there are seven types of approval Personal Protective Equipment (PPE), which requires the approval of the Director General to be used by employees / consumers as one of the engineering control measures. Approval of Personal Protection (AUP) that has been given involving the protection of: -          
    1. PPE - Respiratory Protection (JKKP HIE/12/2/1) 2)
    2. PPE - Hearing Protection (JKKP HIE/12/2/2)
    3. PPE - Eye Protection (JKKP HIE/12/2/3)
    4. PPE - Hand Protection (JKKP HIE/12/2/4)
    5. PPE - Foot Protection (JKKP HIE/12/2/5)
    6. PPE - Body Protection (JKKP HIE/12/2/6)
    7. PPE - Head Protection (JKKP HIE/12/2/7)

    Procedure Of Application

    All applications must be made ​​using the letter head and addressed to: -

    Approval Unit,
    Equipment Section,
    Industrial Hygiene & Ergonomics Division,
    Department of Occupational Safety and Health (DOSH),
    Level 2, Block D3, Complex D,
    Federal Government Administrative Centre,
    62530 Putrajaya.

    Tel: 03-8886 5000/8886 5334
    Fax: 03-8890 1315

    Application Documents

    The following documents should be enclosed with the application: -

    1. Letter Head Application
    2. Original catalogue/brochure and manual on use the equipment
    3. * An approval letter or proof of recognition / endorsement of the equipment by National Approving Authority
    4. * Report of equipment testing from an Accredited Testing Laboratory
    5. Appointment letter as authorized distributor/supplier from origin manufacturer

    Product sample each model and type

    Note :

    1. * Document submitted must be original copy or verify by National Approving Authority / an Accredited Testing Laboratory from SIRIM (M) Sdn. Bhd.
    2. Apply separately for DIFFERENT TYPE of equipment. Please mention below information.
      1. Numbers
      2. Type of equipment
      3. Brand
      4. Model
      5. Manufacturer
      6. Standard
      7. Type of protection


      Approval Process

      DOSH will confirm the documents that have been given or workplace inspection upon receipt of a COMPLETE application information. Decision will be issued within 30 working days from the date COMPLETED application is received.

      Procedure upon approval are as follows: -

      1. Submit a copy of the approval letter or proof of recognition Approve Authority / Inspecting / Testing and Reporting inspection / testing of Approve Authority / Inspecting / Testing of SIRIM (M) Sdn. Bhd to renew the approval.
      2. Inform the department of any change of address, phone number, fax number or status as a legitimate supplier or distributor.
      3. Provide training assistance to users on the selection, use and maintenance of personal protective equipment.
      4. Comply with the instructions issued by the department from time to time. The Department may withdraw approval issued if the information given is incorrect.>
      5. Using a label or logo of approval allowed


      Department Website

      Approval List of Personal Protective Equipment (PPE) are ACTIVE will be uploaded into the Department's website after the approval was given in accordance with the type of protection. Manufacturer, suppliers, distributors, and users can see a list of approvals in the Department's website.

      Any Inquiry / Questions

      Please contact: -

      Approval Unit,
      Equipment Section,
      Industrial Hygiene & Ergonomics Division,
      Department of Occupational Safety and Health (DOSH),
      Level 2, Block D3, Complex D,
      Federal Government Administrative Centre,
      62530 Putrajaya.

      Tel: 03-8886 5000/8886 5334
      Fax: 03-8890 1315

  • Introduction

    For Audiometric Test Center (Static), Factories and Machinery (Noise Exposure) 1989 Regulations, provides for the occupants of a factory / any workplace conduct to determine employee exposure Monitoring shows no employee is exposed to noise levels at or above the action level (equivalent continuous sound market of 85dB (A) or daily noise dose equal to 0.5) the occupier shall provide audiometric testing program for all the employees.

    Procedure Of Application

    All applications must be made ​​using the letter head and addressed to : -
     
    Approval Unit,
    Equipment Section,
    Industrial Hygiene & Ergonomics Division,
    Department of Occupational Safety and Health (DOSH),
    Level 2, Block D3, Complex D,
    Federal Government Administrative Centre,
    62530 Putrajaya.

    Tel: 03-8886 5000/8886 5334
    Fax: 03-8890 1315
     
    Application Documents

    ForAudiometric Test Center (Static), the following documents should be enclosed with the application: -

    1.     Design drawing and location plan of silent booth

    2.     Silent booth and audiometric measuring equipment (approved by DOSH ) calibration report

    3.     Competent training certificate of technician who operates the equipment

    4.     Information of the doctor who supervise the audiometric testing

    5.     Safe Operating Procedure (SOP) for audiometric testing includes format of test report

    For Audiometric Test Center (Mobile), the following documents should be enclosed with the application: -

    1.     Vehicle registration information

    2.     Silent booth design drawing

    3.     Annual calibration report for 'Precision Sound Level Meter Type 1' and 'Sound Level Calibrator Type 1' by manufacturer

    4.     Silent booth and audiometric measuring equipment (approved by DOSH ) calibration report

    5.     Competent training certificate of technician who operates the equipment

    6.     Information of the doctor who supervise the audiometric testing

    7.     Safe Operating Procedure (SOP) for audiometric testing includes method for silent booth calibration and audiometric measuring equipment, a checklist sample for silent booth calibration and audiometric measuring equipment includes format of test report

    Approval Process

    DOSH will confirm the calibration Stationary Audiometric Testing Center upon receipt of a COMPLETE application information. Decision will be issued within 30 working days from the date COMPLETED application is received.

    Procedure upon approval are as follows: -

    i.     Sending the first audiometric test report (after approval) to DOSH
    ii.    Make a silent room calibration and measuring instruments by which the annual audiometric tests conducted on the orders of the calibration or make the Chief Inspector. Copies of calibration records must be submitted to DOSH
    iii.   Make annual calibration tool "Precision Sound Level Meter Type 1, and" Sound Level Calibrator Type 1 "by the makers / manufacturers (PUA - Mobile)
    iv.   Approval will be revoked automatically if permitted sound levels in the room quiet or silent room beyond its limits have been removed from the home.
    v.   DOSH told about any change technician, doctor, location or owner Stationary Audiometric Test Center equipment.
    vi.  Submit a list of places where work audiometric test carried out within a year at the end of the year or early next year and inform DOSH Headquarters and DOSH State Offices within 2 weeks before Audiometric Tests conducted.

     
    Department Website

    ACTIVE Approval List of Audiometric Test Center List (Static)andAudiometric Test Center (Mobile) will be uploaded into the Department's website after the approval is granted
     
    Any Inquiry / Questions

    Please contact: -
    Approval Unit,
    Equipment Section,
    Industrial Hygiene & Ergonomics Division,
    Department of Occupational Safety and Health (DOSH),
    Level 2, Block D3, Complex D,
    Federal Government Administrative Centre,
    62530 Putrajaya.

    Tel: 03-8886 5000/8886 5334
    Fax: 03-8890 1315
  • Panduan Bagi Mendapatkan Kelulusan Rekabentuk dan Pemasangan Lif, Eskalator dan Dumbwaiter (di bawah Peraturan-peraturan Lif Letrik (Penumpang dan Barang-barang) Kilang dan Jentera, 1970)

    Pengenalan

    Pemasangan Lif Letrik Penumpang, Eskalator dan Dumbwaiter hendaklah mendapat kelulusan rekabentuk jentera dari Jabatan Keselamatan dan Kesihatan Pekerjaan, Bahagian Keselamatan Industri, Ibupejabat.

    Peraturan-Peraturan Yang Diperuntukkan

    Syarikat pemasang lif dikehendaki mendapat kelulusan dari Jabatan ini bagi setiap pemasangan lif seperti yang diperuntukkan di dalam Akta Kilang dan Jentera, 1967, di bawah Peraturan-peraturan Lif Letrik (Penumpang dan Barang-barang) Kilang dan Jentera, 1970.

    Tujuan

    Risalah ini dikeluarkan bagi menunjuk arah kepada pemohon untuk mengetahui tatacara kelulusan pemasangan lif dikeluarkan supaya pemasangan lif tersebut adalah selamat kepada pengguna. Jabatan ini memastikan supaya rekabentuk dan pemasangan lif ini mematuhi kehendak-kehendak Peraturan-peraturan Lif Letrik (Penumpang dan Barang-barang) Kilang dan Jentera, 1970.

    Syarat-Syarat Permohonan

    Pemohon yang hendak mendapatkan kelulusan rekabentuk dan pemasangan lif hendaklah mempunyai kelayakan seperti berikut :-
       
    »     Berdaftar dengan jabatan ini sebagai Syarikat Memasang dan Menyelenggara Lif, Eskalator dan Dumbwaiter.
    »     Mempunyai sekurang-kurangnya satu (1) Orang-orang Kompeten yang masih aktif dengan syarikat tersebut dan diiktiraf oleh jabatan ini.

    Dokumen Yang Diperlukan

    Bagi tujuan mendapat kelulusan pemasangan lif, pemunya atau syarikat pemasang lif hendaklah mengemukakan kepada Ketua Pemeriksa Kilang dan Jentera, dua (2) salinan dokumen-dokumen yang berikut:-

    »   Data-data terperinci dan ukuran-ukuran lif seperti yang dikehendaki di Jadual Pertama dalam Akta ini.
    »   Lukisan pelan yang lengkap dan menunjukkan butir-butir dan saiz siap yang berikut :-
    1. Saiz dan kedudukan lubang lif
    2. Butir-butir mengenai litup lubang lif
    3. Saiz, kedudukan, bilangan dan jenis pintu lataran
    4. Saiz dan kedudukan bilik jentera berkaitan dengan lubang lif
    5. Peruntukan laluan ke bilik jentera
    6. Peruntukan bagi gantian udara dan jika boleh, cahaya semulajadi bilik jentera
    7. Bilangan tingkat yang dilayan oleh lif
    8. Tinggi antara setiap tingkat lataran
    9. Bilangan pintu masuk
    10. Jumlah ruang atas
    11. Ketinggian bilik jentera
    12. Kedalaman lubang pit
    »  Sijil-sijil atau perakuan yang dikeluarkan oleh pembuat lif berkenaan:-
    1. Perakuan menyatakan bahawa lif itu telah direkabentuk dan dibina menurut peraturan-peraturan ini setakat mana peruntukan-peruntukan ini dipakai baginya. 
    2. Perakuan menyatakan bahawa rekabentuk giar keselamatan dan rekabentuk penampan jenis minyak telah berjaya dalam ujian-ujian, termasuk ujian laju lampau di bawah beban kontrak penuh.
    3. Perakuan menyatakan bahawa tebatan bagi bahagian-bahagian letrik semua pengawal pesawat mengunci pintu lataran, pesawat merentikan kereta lif pada hujung perjalanan, suis get, suis-suis pintu kereta lif, dan pesawat kendalian yang lain dan yang seumpamanya telah berjaya dalam ujian, dengan menggunakan voltan arus ulang alik sama dengan sepuluh kali voltan kerja, dengan voltan maksima dua ribu voltan selama tidak kurang daripada satu minit apabila dikenakan :-Perakuan menyatakan garis pusat, binaan, mutu dan kekekuatan tensil tali-tali pengantung.
      1. Di antara bahagian hidup dengan kotak-kotak atau rangka bina dengan semua litar-litar tertutup
      2. Di antara terminal-terminal utama atau bahagian-bahagian yang bersamaan dengan semua litar terbuka
      3. Di antara mana-mana bahagian litar hidup atau litar-litar berasinganiv Perakuan menyatakan garis pusat, binaan, mutu dan kekekuatan tensil tali-tali pengantung.
    4. Perakuan menyatakan garis pusat, binaan, mutu dan kekekuatan tensil tali-tali pengantung.
  • Introduction

    Regulation 5 of the Regulations Factories and Machinery (Mineral Dust) 1989, Sand Blasting provides that the process cannot be used in any factory unless prior written authorization from the Chief Inspector.

    "Sand Blasting" construed as cleaning, smoothing, roughening, cutting, surface preparation or removal of surface or part of any building, ship or goods by using sand or other materials containing crystalline silica that is driven by compressed air or steam blast or a wheel or any other similar means.

    "Crystalline Silica" refers to crystalline forms of silica include quartz independent, and tridimit kristobolit.

    "Silica-Free" refers to silica dioxide is not affiliated with any other element or compound.
     
    Procedure Of Application

    All applications must be made ​​using the letter head and addressed to : -
     
    Approval Unit,
    Equipment Section,
    Industrial Hygiene & Ergonomics Division,
    Department of Occupational Safety and Health (DOSH),
    Level 2, Block D3, Complex D,
    Federal Government Administrative Centre,
    62530 Putrajaya.
    Tel: 03-8886 5000/8886 5334
    Fax: 03-8890 1315
     
    Application Documents

    The following documents should be enclosed with the application: -

    1.      Information about the applicants
    2.      Blasting machine information include serial number, model & power
    3.      Design drawing or catalogue of blasting machine
    4.      A complete Chemical Safety Data Sheet (CSDS)
    5.      Safe Operating Procedure (SOP) for sand blasting process
    6.      Other related process flow chart
    7.      Information for safety precaution provided such as PPE issued, warning sign etc
    8.      Key plan to blasting site for inspection visit
     
    Approval Process

    DOSH will make an inspection visit Sand Blasting Process after receiving information that COMPLETED application. Decision will be issued within 30 working days from the date COMPLETED application is received.

    Procedure upon approval are as follows: -

    i.     Comply with Section 15 of the Occupational Health and Safety Act, 1994 to ensure so far as is practicable, the safety, health and welfare of workers who handle machinery.

    ii.    Comply with the Occupational Safety and Health (Use and Standard of Exposure of Chemicals Hazardous to Health, Regulations 2000).

    iii.    Seeking approval from DOSH Headquarters should be converted to media blasting material other than those mentioned above, as required under the Regulations Factories and Machinery Act 1967 (Regulation 6 of the Mineral Dust Regulations 1989)that if the material contains percent free crystalline silica (free crystalline silica) is less than 1% at concentrations exceeding 5mg/m3 for 'respirator dust' or 10mg/m3 for 'total dust' on a weighted average period of 8 hours (TWA8).

    iv.     Getting permission to install and operate the blasting machine and other related machinery from the Director, Department of Occupational Safety and Health in the land-related .

    Any Inquiry / Questions

    Please contact: -

    Approval Unit,
    Equipment Section,
    Industrial Hygiene & Ergonomics Division,
    Department of Occupational Safety and Health (DOSH),
    Level 2, Block D3, Complex D,
    Federal Government Administrative Centre,
    62530 Putrajaya.

    Tel: 03-8886 5000/8886 5334
    Fax: 03-8890 1315
  • Guidelines For Approval Of Hoisting Machine Design

    Preamble

    Every hoisting machine which is power driven by electricity, diesel, pneumatic and other means for lifting, raising or lowering load except manual hoist and material handling equipment shall possess a valid Certificate of Fitness. The design of every hoisting machine must be appraised by Design Section of the Department of Occupational Safety and Health before the machine is been fabricated, installed and used.

    Hoisting Machine Categories

    There are four categories of hoisting machine under this guideline:

    Category Description
    A
    Hoisting machine which is designed, customized and fabricated according to the user’s needs and specification
    B
    Mass produced hoisting machine
    C
    Amusement park ride and other type of hoisting machine which is not under category A, B & D
    D
    Hoisting machine usually used at offshore and construction site

    The list of type of hoisting machine in each of those categories can be found in Appendix 2

    Fabrication of Hoisting Machine

    All hoisting machine made locally must be fabricated by a Competent Firm registered with the Department of Occupational Safety and Health

    Model Re-Confirmation for Mobile Crane, Crawler Crane, Truck Mounted Crane, Injection Type Piling Machine, Auger Crane and Mobile Elevating Work Platform

    The approval of these type of machine is based on model. Applicant can write in officially or apply online through SKUD system for inquiry on whether the said model had been approved.

    Change of Hoist of the Same Model (for OTC and Monorail only)

    When there is a change of new unit of hoist of the same maker and model of the existing approved OTC and monorail design, there is no requirement to resubmit another design approval. Owner is to notify the change of the said hoist to DOSH State Office.

    Change of Hoist of a Different Model (for OTC and Monorail only)

    When there is a change of new unit of hoist of different maker and model of the existing approved OTC and monorail design, a new submission for design approval is required. Applicant is to clearly state in the official application letter for design approval of this change of hoist.

    Hoist More Than 5 Years (for OTC and Monorail only)

    If the hoist intended to be used is more than 5 years after its fabrication date, the competent firm should carry out an integrity test and re-certify the hoist before submitting the design approval.

    Exemption

    Design approval is not required for monorail crane with safe working load of 4 tons and below only, provided that the girder is of I or H beam of standard properties. However, this type of monorail crane still requires a basic engineering drawing and calculation which are endorsed by a local Professional Engineer before registering with DOSH State office.

    In addition, the following hoisting machines are exempted from obtaining design approval and certificate of fitness:-

    1. Boring rig
    2. Drilling rig
    3. Piling machine mounted on crawler track only
    4. Winch for towing vehicle only
    5. Dock leveler
    6. Manipulator
    7. Gangway tower
    8. Vertical conveyor
    9. Tail lift
    10. Automatic Storage and Retrieval System (ASRS)
    11. Monkey hoist with maximum lifting load of 80kg and maximum lifting height of 9m only
    12. Air or pneumatic hoist with maximum safe working load of 500kg only

    Re-Engineering

    All re-engineered machine must be re-evaluated, re-drawn and re-calculate by a competent firm registered with the Department of Occupational Safety and Health in the scope of the said hoisting machine. Applicant is to clearly state in the official application letter for design approval that it is a re-engineered hoisting machine.

    Modification

    Any modification to the existing approved design will cause the current Certificate of Fitness to be revoked and the modified design shall be re-submitted for appraisal. Modification can only be carried out by registered competent firm in the scope of the said hoisting machine or the original manufacturer. Applicant is to clearly state in the official application letter for design approval that the said hoisting machine has been modified.

    Erection, Maintenance and Dismantling

    Certain machinery such as tower crane, passenger hoist, mast climbing work platform, gondola (suspended platform) and self climbing scaffolding system required to be erected by a competent firm registered with the Department of Occupational Safety and Health.

    Such appointment letter shall be attached with the submission should the applicant is other than the competent firm.

    Client Charter

    All applications submitted online will be processed within 30 days from the date of submission.

    System Requirements

    The online application system, SKUD (http://skud.dosh.gov.my:88/default.aspx) is best viewed with Internet Explorer 7 & 8. Other internet browsers (e.g. Firefox, Chrome, Safari) are not compatible with the system. If using Internet Explorer 9 and above, please adjust the compatibility view setting (under “tools” at the menu bar) in order to access the system.

    APPENDIX 1 - DETAILS OF DOCUMENTS FOR DESIGN APPROVAL OF HOISTING MACHINE

    APPENDIX 2 - DOCUMENTS BY CATEGORY AND TYPE OF HOISTING MACHINE

    APPENDIX 3 - SAFETY DEVICES / FEATURES ON TOWER CRANES

    APPENDIX FOR GOODS HOIST

    APPENDIX FOR SCISSOR LIFT

     


    Question

    Any questions may be asked to:

    Hoisting Machine Unit
    Design Section
    Industrial Safety Division
    Department of Occupational Safety and Health
    Level 3, Block D3, Parcel D
    Federal Government Administrative Centre
    62530 W. P. Putrajaya
    Tel : 03 – 8886 5342
    Fax : 03 – 8889 2349

  • APPLICATIONS FOR PERMISSION TO INSTALL (PTI) AND TO OPERATE (PTO) PETROLEUM PIPELINES, BULK STORAGE FACILITY AND EQUIPMENT

    Introduction 
       
    In October 1992, the Ministry of Domestic Trade and Consumer Affairs was given the responsibility of administrating the Petroleum (Safety Measures) Act 1984 and the regulations made thereunder. This act governs the safety of the petroleum industry which encompasses the safety aspect of the transport, storage, handling and utilisation of petroleum equipment/appliances. To ensure the smooth enforcement of this Act, DOSH was entrusted by the ministry to implement one of the regulations under this act, i.e. Petroleum (Safety Measures) (Transport of Petroleum by Pipelines) Regulations 1985.
     
    Aim

    This guide is intended to explain the application procedures for permission to install (PTI)/permission to operate (PTO) petroleum pipelines, bulk storage facility and equipment. The applications are classified into four categories;
        
     i.   Permission to install (PTI) petroleum pipelines
          ii.   Permission to operate (PTO) petroleum pipelines
          iii.   Permission to install (PTI) liquefied petroleum gas (/LPG) storage facility and gas fuel pipeline system to combustors (appliances)
          iv.   Petroleum equipment approval

    Definition

     i.  Petroleum

    Any mineral oil or relative hydrocarbon and natural gas existing in its natural condition and casing head petroleum spirit including bituminous shales and other stratified deposits from which oil can be extracted, including petroleum products.

    ii.  Petroleum Products

    All substances that are derived from petroleum:
    • Methane, ethane, propane, butane or hydrocarbon which may consist of one or more of the above gases either in the form of gas or liquid (e.g.: natural gas and LPG)           
    • Gasoline
    • Naphtha         
    • Reformate           
    • Kerosene           
    • Diesel          
    • Fuel Gas           
    • Base oil        
    • Lubricating oil         
    • Asphalt / Bitumen          
    • Grease and Wax

    iii.  Petroleum Pipelines

    Petroleum pipelines are all parts of those physical facilities through which the petroleum moves in transport including pipes, valves and other appurtenances attached to the pipes, pumps, compressor units, meters, regulators and fabricated assemblies.

    iv.  Bulk Storage Facility

    Liquefied petroleum gas (LPG) storage system from tanks or cylinders (exceeding two 50-kg industrial cylinders)

     v.  Petroleum Equipment

    Petroleum equipment is all parts of those physical facilities attached to the petroleum pipelines such as the valves, meters and regulators.

    Scope of Application of the Petroleum (Transport by Pipelines) Regulations 1985

    i.     Permission to Install (PTI) and Operate (PTO) Petroleum Pipelines           

    Applications for PTI and PTO should be submitted for:

    a) Pipelines transporting liquefied petroleum between production facilities, tank farms, natural gas processing plants, refineries, service stations, terminals (marine, rail and truck) and other delivery and receiving points.

    b) Pipelines transporting natural gas from the outlet of separators or traps at oil wells until the outlet of the customer's meter set assembly including gas processing plants, and metering and regulating stations. (Installation of pipelines after the city gate station until before the metering and regulating station in the factory is subject to the Gas Supplies Act 1993.)

    All design, fabrication, installation, testing and the safety aspect of the operation and maintenance of pipelines transporting natural gas shall meet the ASME B 31.8 Code of Standards, and ASME B 31.4 Code of Standards for pipelines transporting liquefied petroleum. See Diagram 1.

    ii.     Permission to Install (PTI) Liquefied Petroleum Gas (LPG) Bulk Storage Facility and Gas Fuel Pipeline System to Combustors (Appliances)           

    All substances that are derived from petroleum, i.e.:

    a. Installation of two or more LPG cylinders in factory premises. See Diagram 2.
    b. Installation of two liquid outlet system LPG cylinders in any premises.
    c. Installation of LPG bulk tank (200 kg, 2.5 kL, 10 kL, 60 KL, etc) in any premises. See Diagram 3.
    d. Installation of gas (fuel gas) pipelines in factory premises. See Diagram 4.
    e. Installation of gas (fuel gas) pipelines in power plants and petrochemical plants. See Diagram 1.

    All designs, installation, testing and the safety aspect of the installation of systems a, b, d and d above shall comply with the MS 830 and MS 930 design code.           
    Meanwhile, for the installation of system d, the design code applicable is ASME B 31.1 (installation of gas pipelines in power plant) and ASME B 31.3 (installation pipelines in petrochemical plant).

    iii.     Petroleum Equipment Approval   

    Application for approval of the use of petroleum equipment shall be obtained for all types of valve (e.g. ball valve, check valve, gate valve, meters, regulators, monolithic joints).

    Application


    Applications for permission to install (PTI)/operate (PTO) pipelines and bulk storage facility as well as petroleum equipment approval should be submitted through an official letter together with a checklist of supporting documents and addressed to:

    Director-General
    Department of Occupational Safety and Health
    Levels 2, 3 & 4, Block D3, Complex D,
    Federal Government Administrative Centre
    62530 Putrajaya

    Applications by hand should be submitted at the Service Counter at Level 3 of the above address.

    The following are forms and supporting documents which need to be submitted with the application:

    1. icon Permission to install (PTI) petroleum pipeline (TPSP 1)
    2. icon Permission to operate (PTO) petroleum pipeline (TPSP 2)
    3. icon Permission to install (PTI) liquefied petroleum gas (LPG) bulk storage facility and fuel gas pipeline (TPSP 3)
    4. icon Petroleum equipment approval (TPSP 4)


    Client Charter
      

    An application submitted with the complete documents will be processed within 15 working days of receipt.


    Flow Chart of Application Process
    Application Process Flow Chart dl unguve


    Relevant Information

    JKKP BP1 – Confirmation of Pipeline Welding dl unguve 
    TPSP 2a – Acknowledgement of Confirmation according to Regulation 6(2)(a) from contractor dl unguve
    TPSP 2b – Acknowledgement of Confirmation according to Regulation 6(2)(2) from owner dl unguve
    DS-02-007 – Petroleum Pipeline Inspection and Hydrostatic Test Form dl unguve
    Record of Liquefied Petroleum Gas System Installation Inspection and Leakage Test dl unguve
    Record of Installation Inspection and Leakage Test of the Natural Gas Piping System from Metering Station to Combustor dl unguve



  • Introduction To Unfired Pressure Vessels

    Under the Factories and Machinery Act 1967, each unfired pressure vessel must have a valid certificate of fitness (CF) before it can be operated. For this purpose, approval for the design of the unfired pressure vessel has to be obtained in advance from the Department of Occupational Safety and Health (DOSH) before it fabricated, installed or used.

    Application for approval of the design may be made by the manufacturing company, installer, supplier or owner of the unfired pressure vessel. Local manufacturers of unfired pressure vessels must register as a manufacturer with the department.

    The following are several examples of unfired pressure vessels that require design approval:
    • Air container
    • Steriliser
    • LPG storage tank
    • Heat Exchanger
    • Pressure vessels at the petrochemical plants etc

    Information to be submitted for approval of the design of unfired pressure vessels:

    icon Application for Unfired Pressure Vessel Design Approval (Import, IDxDP equal or less than 3000psig-in)

    icon Application for Unfired Pressure Vessel Design Approval (Import, IDxDP more than 3000psig-in)

    icon Application for Unfired Pressure Vessel Design Approval (Local Manufacturer recognized by Department)

    icon Application for Unfired Pressure Vessel Design Approval (Used)

    icon Example of Design Drawing

    For further enquiries, please contact the On Duty Officer

    Unfired Pressure Vessel Unit,
    Industrial Safety Division,
    Department of Occupational Safety and Health,
    Level 3, Block D3, Complex D,
    Federal Government Administrative Centre
    62530 Putrajaya

    Tel: 603-8886 5342
    Fax: 603-8889 2349

  • Introduction To Steam Boilers

    Under the Factories and Machinery Act 1967, each steam boiler to be manufactured or brought into this country needs a valid certificate of fitness (CF) before it may be used. Therefore, approval of the steam boiler design needs to be obtained in advance from the Department of Occupational Safety and Health (DOSH) before it can be manufactured, installed or used.

    Application may be made by the manufacturing company, installer, supplier or owner of the steam boiler. Local boiler manufacturers need to register as a manufacturer with the department

    The following are several examples of steam boilers that must be registered:

     1.     Water tube steam boiler
     2.     Fire tube steam boiler
     3.     Electric steam boiler
     4.     Waste heat recovery boiler

    Equipment such as the thermal oil heater and hot water boiler too need to be registered although they do not produce steam.

    The following is the information needed for approval of the steam boiler design:

    Application for boiler design (Imported & Local) dl unguve
    Application for boiler design (Used) dl unguve


    Further enquiries may be directed to:


    Head of the Steam Boiler Unit,
    Steam Boiler Unit,
    Industrial Safety Division,
    Level 3, Block D3, Complex D,
    Federal Government Administrative Centre
    62530 Putrajaya

    Tel: +603-88865353
    Fax: +603-88892349
  • Aim

    This procedure aims to explain the application to carry out hydrostatic or operating test which is witnessed by a DOSH officer.

    Procedure
    1. The steam boiler or pressure vessel to be tested has obtained design approval (new machinery) or repair approval (registered machinery).
    2. Submit application letter to carry out the test on the machinery to the State DOSH Office where the test will be carried out.
    3. Contact DOSH office to set a test date not later than one week from the date of the test.
    4. Submit information on the machinery such as copy of letter of approval, manufacturer's data report, welder record and other related information to DOSH officer before the test is carried out.
    Flow Chart

    Obtain letter of approval:

    i.     Design
    ii. Repair approval

    arrow 130

    Send application letter to DOSH office

    arrow 130

    Contact DOSH office to set test date

    arrow 130

    Submit relevant information to DOSH officer

Support Center

For any official matter at DOSH Headquarters, please proceed to:

Level 4 (Main Counter), Block D3, Complex D, Federal Government Administrative Centre, 62530 Putrajaya
(T): 03-8886 5343
(F): 03-8889 2443
(E): This email address is being protected from spambots. You need JavaScript enabled to view it.
(W): www.dosh.gov.my

Visitors Counter

020310594
Today
Yesterday
This Week
Last Week
This Month
Last Month
All days
820
20941
125419
20030042
125419
612456
20310594